==Required manual steps==
 
  +
==Release engineering environment==
  +
  +
Release engineering operations are currently performed on a Ubuntu 18.04 host. Updates to the Ubuntu version may cause churn in the generated files which are checked into the repository due to newer versions of programs in the toolchain.
  +
  +
The release engineering host must have the following packages installed:
  +
  +
* autoconf
  +
* bison
  +
* build-essential
  +
* dejagnu
  +
* doxygen
  +
* flex
  +
* git
  +
* keyutils
  +
* ldap-utils
  +
* libcmocka-dev
  +
* libkeyutils-dev
  +
* libldap2-dev
  +
* liblmdb-dev
  +
* libresolv-wrapper
  +
* libsasl2-dev
  +
* libssl-dev
  +
* libtool
  +
* pkg-config
  +
* python-sphinx
  +
* python-cheetah
  +
* rcs
  +
* slapd
  +
* tcl-dev
  +
* texlive
  +
* texlive-latex-extra
  +
  +
==Pulling up changes to release branches==
  +
  +
* For each supported release (usually the most recent and one previous release), prepare a git working copy with the krb5-x.y branch checked out from the authoritative repository. From the krbdev-services repository, copy githooks/hookutils.py and githooks-client/prepare-commit-msg into .git/hooks for both working copies.
  +
  +
* Check that each working copy is clean, has no unexpected extra commits, and is up to date with the authoritative repository. Checking the output of "git status" and running "git pull" should accomplish this.
  +
  +
* At https://krbdev.mit.edu:444/rt/ , start a new search, add the term "queue is krb5", then the criteria "tags is pullup", then search. It can be useful to create a browser tab for each search result.
  +
  +
* If there has been a calendar year change since the last patch release, pull up the commit(s) which bump the project-wide copyright years as well.
  +
  +
* For each release branch:
  +
** For each ticket marked for pullup to that branch:
  +
*** For each commit listed in the ticket, run "KRB5_VERSION_FIXED=x.y.z git cherry-pick -x COMMIT", and address any merge conflicts. x.y.z should be the next patch release that will be created on the release branch. If there are merge conflicts, "git cherry-pick --continue" will not apply the log message hook, so edit the RT fields manually.
  +
*** Examine the commits any consider any possible interactions with changes made since the release branch.
  +
*** Run "make" and "make check". Remember that "make check" will not work for multiple working directories concurrently on the same host.
  +
*** If the change isn't covered by automated tests, consider testing it by hand.
  +
* Consider pushing the updated release branches to a personal github fork and waiting for Github Actions to finish building and testing it.
  +
* If the pulled up changes are substantial, consider running a build and check of each release branch on krbdev-sparc-build.
  +
* Push the updated release branches to the authoritative repository.
  +
* Remove the "pullup" tag from each ticket. This can be done in a bulk update from the search result page, or it can be done on each ticket individually from the jumbo page.
  +
  +
==Creating a new release branch==
  +
  +
* At https://krbdev.mit.edu:444/rt/ , go to Admin -> Custom Fields -> Target_version and add x.y and x.y-next values. Do the same for Version_Fixed.
  +
* At https://krbdev.mit.edu:444/rt/ , perform a search with the following criteria:
  +
** Queue is krb5
  +
** Status is resolved
  +
** Version_Fixed is (no value)
  +
** Tags is not unsupported
  +
** Tags is not noresource
  +
** Tags is not nochange
  +
* Verify that the resulting list of tickets are all for changes introduced in the past development cycle, and bulk update them to have Version_Fixed x.y.
  +
* On the master branch, update doc/mitK5features.rst, updating the "Latest stable" and "Supported" release numbers. Write up a list of major changes for the new release, broken down by category. Code quality changes usually do not have associated tickets, so review the version history for commits with no RT headers. Commit with the subject "Update features list for x.y".
  +
* On the master branch, update <code>config.guess</code> and <code>config.sub</code> from <code>git://git.savannah.gnu.org/config.git</code>. Commit with the subject "Update config.guess, config.sub"
  +
* On the master branch, run "make regen". Commit with the subject "make regen". Push the master branch to the authoritative repository.
  +
* Create the new branch and push it to the authoritative repository.
  +
* On the new branch, update README for the new release:
  +
** Make sure that all x.y references are for the new version (they should be already).
  +
** Update any notes about transitions (such as enctype deprecations) and add new ones if necessary.
  +
** Include the list of major changes for the new release.
  +
** Include the list of tickets changed (copy-paste from https://krbdev.mit.edu/rt/NoAuth/krb5-x.y/fixed-x.y.z.html).
  +
** Copy the list of contributors from the previous release branch.
  +
** Add contributors from the RT tickets for the new release branch.
  +
** Commit with the message "Update README for krb5-x.y" and push to the authoritative repository.
  +
* On the master branch, update README for the next prerelease:
  +
** In README, update x.y references to x.(y+1), and update the list of contributors and any changes to transitional notes from the x.y branch.
  +
** In src/patchlevel.h, update KRB5_MINOR_RELEASE to y+1.
  +
** Commit with the message "Updates for krb5-x.(y+1)-prerelease" and push to the authoritative repository.
  +
* Update web pages
  +
** Create directory /mit/kerberos/dist/krb5/x.y and copy HEADER from a previous directory
  +
** Create directories /mit/kerberos/krb5-x.y and /mit/kerberos/krb5-x.y/RCS
  +
  +
==Preparing releases==
   
 
===Pre-mkrel===
 
===Pre-mkrel===
   
* make depend
 
  +
* check copyright years in project-wide stuff
* update patchlevel.h
 
  +
* make sure you're in a build tree that's not the source tree and configured using <code>--enable-maintainer-mode</code>
* regenerate manpages
 
  +
* <code>make regen</code> and commit if there is more than just a pot file date change, with the commit message "make regen"
* regenerate localization template
 
  +
* manually edit patchlevel.h to reflect the new release
* update README
 
  +
** for a patch release, increment KRB5_PATCHLEVEL, change the next line to "/* #undef KRB5_RELTAIL */", and change KRB5_RELTAG to "krb5-x.y.z-final"
** dates
 
  +
** for an alpha or beta release, set KRB5_RELTAIL to "beta1" or similar, and change KRB5_RELTAG to "krb5-x.y-beta1" or similar.
  +
* manually update README
  +
** release dates (in major changes heading, ISO 8601 date format with hyphens)
  +
*** we do not have release dates for alpha or beta releases; add one when making the first final x.y release
 
** changes
 
** changes
** contributors
 
  +
*** note whether bugfix release, maintenance vs current release
  +
*** bullet list of major changes
  +
*** minor changes = list of RT tickets fixed -- always grab a fresh list from RT when editing these! (https://krbdev.mit.edu/rt/NoAuth/krb5-x.y/fixed-x.y.z.html)
  +
** contributors (RT is a good source for these; click through the ticket links from the above URL and look for reporter and patch author names)
  +
** double-check dates and release numbers in new section headings
  +
* re-run <code>make regen</code> with updated patchlevel.h
  +
* commit the README, patchlevel-specific man page, and template changes with the subject "Update for krb5-x.y.z"
  +
* <code>git tag krb5-x.y.z-final</code> (or <code>krb5-x.y-beta1</code> or similar for an alpha or beta release)
  +
  +
===Running mkrel===
  +
  +
* <code>path_to_mkrel/mkrel --repository $YOUR_SOURCE_TREE krb5-x.y.z-final krb5-x.y.z</code>
  +
** For an alpha or beta release, <code>path_to_mkrel/mkrel --repository $YOUR_SOURCE_TREE krb5-x.y-beta1 krb5-x.y-beta1</code> or similar
  +
* manually inspect output for versioning and correctness
  +
** HTML docs
  +
** PDF docs
  +
** patchlevel.h as modified by mkrel
  +
* push release branch commits and release tags to authoritative repository
  +
** you will need to be in hooks.branchers in the authoritative repository to push the tags
   
 
===Post-mkrel===
 
===Post-mkrel===
   
* PGP sign
 
  +
* PGP sign (<code>gpg -ab krb5-x.y.z.tar.gz</code>, generates krb5-x.y.z.tar.gz.asc)
  +
* copy tar file and signature into /mit/kerberos/dist/krb5/x.y
  +
* for alpha and beta releases:
  +
** create /mit/kerberos/krb5-x.y/krb5-x.y.html based on the first commit from a previous release
  +
** symlink index.html to krb5-x.y.html in that directory
  +
** place an entry in /mit/kerberos/dist/testing.html
  +
** send an announcement to krbdev@mit.edu
  +
** edit src/patchlevel.h, changing KRB5_RELTAIL to "beta1-postrelease" (or similar) and KRB5_RELTAG to "krb5-x.y". Commit with the subject "Update for krb5-x.y-beta1-postrelease" or similar and push to the authoritative repository.
  +
** skip all remaining steps
  +
* create /mit/kerberos/krb5-x.y/krb5-x.y.z and /mit/kerberos/krb5-x.y/krb5-x.y.z/doc
  +
* copy signature to /mit/kerberos/krb5-x.y/krb5-x.y.z.sig
  +
* copy README from release source code to /mit/kerberos/krb5-x.y/README-x.y.z.txt
 
* generate branded HTML docs
 
* generate branded HTML docs
  +
** <code>HTML_LOGO=/mit/kerberos/mitkc-logo-sm.png make html</code>
  +
** we don't ship the branded (with logo) docs because the logo is an MIT trademark
  +
** copy the resulting documentation tree to /mit/kerberos/krb5-x.y/krb5-x.y.z/doc/html
  +
** repeat for <code>HTML_LOGO=... make pdf</code> and .../doc/pdf
  +
* update RT configuration
  +
** check that https://krbdev.mit.edu/rt/NoAuth/krb5-x.y/fixed-x.y.z.html and .../bugs-x.y.z.html work
  +
** in the web interface, to go Admin -> Custom Fields -> Version_Fixed and add a new one for the next patch release
 
* edit web pages
 
* edit web pages
* send announcement
 
  +
** create /mit/kerberos/krb5-x.y/krb5-x.y.z.html and check it into RCS, using similar files as an example (for the first x.y release, update krb5-x.y.html using the previous release's krb5-x.y.html as an example)
  +
** update /mit/kerberos/index.html with the new release numbers (possibly removing out-of-service releases) and add entries to the "Recent news" section; add old release entries to historical.html and old news items to oldnews.html
  +
** update /mit/kerberos/dist/index.html with new release references (possibly removing out-of-service releases); add old entries to historic.html
  +
** review edited web pages in a web browser and double check that release numbers and release dates have been updated
  +
** update /mit/kerberos/krb5-x.y/doc and /mit/kerberos/krb5-x.y/index.html symlinks
  +
** update /mit/kerberos/krb5-latest symlink if this is a major or minor release
  +
** for the first final krb5-x.y release, remove the entry from /mit/kerberos/dist/testing.html
  +
* send announcement to kerberos-announce
  +
* make followup versioning commit to release branch
  +
** edit src/patchlevel.h, setting KRB5_RELTAIL to "postrelease" and KRB5_RELTAG to "krb5-x.y"
  +
** use the commit message "Update for krb5-x.y.z-postrelease"
  +
** push this commit to the authoritative repository

Latest revision as of 13:44, 6 July 2023

Release engineering environment

Release engineering operations are currently performed on a Ubuntu 18.04 host. Updates to the Ubuntu version may cause churn in the generated files which are checked into the repository due to newer versions of programs in the toolchain.

The release engineering host must have the following packages installed:

  • autoconf
  • bison
  • build-essential
  • dejagnu
  • doxygen
  • flex
  • git
  • keyutils
  • ldap-utils
  • libcmocka-dev
  • libkeyutils-dev
  • libldap2-dev
  • liblmdb-dev
  • libresolv-wrapper
  • libsasl2-dev
  • libssl-dev
  • libtool
  • pkg-config
  • python-sphinx
  • python-cheetah
  • rcs
  • slapd
  • tcl-dev
  • texlive
  • texlive-latex-extra

Pulling up changes to release branches

  • For each supported release (usually the most recent and one previous release), prepare a git working copy with the krb5-x.y branch checked out from the authoritative repository. From the krbdev-services repository, copy githooks/hookutils.py and githooks-client/prepare-commit-msg into .git/hooks for both working copies.
  • Check that each working copy is clean, has no unexpected extra commits, and is up to date with the authoritative repository. Checking the output of "git status" and running "git pull" should accomplish this.
  • At https://krbdev.mit.edu:444/rt/ , start a new search, add the term "queue is krb5", then the criteria "tags is pullup", then search. It can be useful to create a browser tab for each search result.
  • If there has been a calendar year change since the last patch release, pull up the commit(s) which bump the project-wide copyright years as well.
  • For each release branch:
    • For each ticket marked for pullup to that branch:
      • For each commit listed in the ticket, run "KRB5_VERSION_FIXED=x.y.z git cherry-pick -x COMMIT", and address any merge conflicts. x.y.z should be the next patch release that will be created on the release branch. If there are merge conflicts, "git cherry-pick --continue" will not apply the log message hook, so edit the RT fields manually.
      • Examine the commits any consider any possible interactions with changes made since the release branch.
      • Run "make" and "make check". Remember that "make check" will not work for multiple working directories concurrently on the same host.
      • If the change isn't covered by automated tests, consider testing it by hand.
  • Consider pushing the updated release branches to a personal github fork and waiting for Github Actions to finish building and testing it.
  • If the pulled up changes are substantial, consider running a build and check of each release branch on krbdev-sparc-build.
  • Push the updated release branches to the authoritative repository.
  • Remove the "pullup" tag from each ticket. This can be done in a bulk update from the search result page, or it can be done on each ticket individually from the jumbo page.

Creating a new release branch

  • At https://krbdev.mit.edu:444/rt/ , go to Admin -> Custom Fields -> Target_version and add x.y and x.y-next values. Do the same for Version_Fixed.
  • At https://krbdev.mit.edu:444/rt/ , perform a search with the following criteria:
    • Queue is krb5
    • Status is resolved
    • Version_Fixed is (no value)
    • Tags is not unsupported
    • Tags is not noresource
    • Tags is not nochange
  • Verify that the resulting list of tickets are all for changes introduced in the past development cycle, and bulk update them to have Version_Fixed x.y.
  • On the master branch, update doc/mitK5features.rst, updating the "Latest stable" and "Supported" release numbers. Write up a list of major changes for the new release, broken down by category. Code quality changes usually do not have associated tickets, so review the version history for commits with no RT headers. Commit with the subject "Update features list for x.y".
  • On the master branch, update config.guess and config.sub from git://git.savannah.gnu.org/config.git. Commit with the subject "Update config.guess, config.sub"
  • On the master branch, run "make regen". Commit with the subject "make regen". Push the master branch to the authoritative repository.
  • Create the new branch and push it to the authoritative repository.
  • On the new branch, update README for the new release:
    • Make sure that all x.y references are for the new version (they should be already).
    • Update any notes about transitions (such as enctype deprecations) and add new ones if necessary.
    • Include the list of major changes for the new release.
    • Include the list of tickets changed (copy-paste from https://krbdev.mit.edu/rt/NoAuth/krb5-x.y/fixed-x.y.z.html).
    • Copy the list of contributors from the previous release branch.
    • Add contributors from the RT tickets for the new release branch.
    • Commit with the message "Update README for krb5-x.y" and push to the authoritative repository.
  • On the master branch, update README for the next prerelease:
    • In README, update x.y references to x.(y+1), and update the list of contributors and any changes to transitional notes from the x.y branch.
    • In src/patchlevel.h, update KRB5_MINOR_RELEASE to y+1.
    • Commit with the message "Updates for krb5-x.(y+1)-prerelease" and push to the authoritative repository.
  • Update web pages
    • Create directory /mit/kerberos/dist/krb5/x.y and copy HEADER from a previous directory
    • Create directories /mit/kerberos/krb5-x.y and /mit/kerberos/krb5-x.y/RCS

Preparing releases

Pre-mkrel

  • check copyright years in project-wide stuff
  • make sure you're in a build tree that's not the source tree and configured using --enable-maintainer-mode
  • make regen and commit if there is more than just a pot file date change, with the commit message "make regen"
  • manually edit patchlevel.h to reflect the new release
    • for a patch release, increment KRB5_PATCHLEVEL, change the next line to "/* #undef KRB5_RELTAIL */", and change KRB5_RELTAG to "krb5-x.y.z-final"
    • for an alpha or beta release, set KRB5_RELTAIL to "beta1" or similar, and change KRB5_RELTAG to "krb5-x.y-beta1" or similar.
  • manually update README
    • release dates (in major changes heading, ISO 8601 date format with hyphens)
      • we do not have release dates for alpha or beta releases; add one when making the first final x.y release
    • changes
    • contributors (RT is a good source for these; click through the ticket links from the above URL and look for reporter and patch author names)
    • double-check dates and release numbers in new section headings
  • re-run make regen with updated patchlevel.h
  • commit the README, patchlevel-specific man page, and template changes with the subject "Update for krb5-x.y.z"
  • git tag krb5-x.y.z-final (or krb5-x.y-beta1 or similar for an alpha or beta release)

Running mkrel

  • path_to_mkrel/mkrel --repository $YOUR_SOURCE_TREE krb5-x.y.z-final krb5-x.y.z
    • For an alpha or beta release, path_to_mkrel/mkrel --repository $YOUR_SOURCE_TREE krb5-x.y-beta1 krb5-x.y-beta1 or similar
  • manually inspect output for versioning and correctness
    • HTML docs
    • PDF docs
    • patchlevel.h as modified by mkrel
  • push release branch commits and release tags to authoritative repository
    • you will need to be in hooks.branchers in the authoritative repository to push the tags

Post-mkrel

  • PGP sign (gpg -ab krb5-x.y.z.tar.gz, generates krb5-x.y.z.tar.gz.asc)
  • copy tar file and signature into /mit/kerberos/dist/krb5/x.y
  • for alpha and beta releases:
    • create /mit/kerberos/krb5-x.y/krb5-x.y.html based on the first commit from a previous release
    • symlink index.html to krb5-x.y.html in that directory
    • place an entry in /mit/kerberos/dist/testing.html
    • send an announcement to krbdev@mit.edu
    • edit src/patchlevel.h, changing KRB5_RELTAIL to "beta1-postrelease" (or similar) and KRB5_RELTAG to "krb5-x.y". Commit with the subject "Update for krb5-x.y-beta1-postrelease" or similar and push to the authoritative repository.
    • skip all remaining steps
  • create /mit/kerberos/krb5-x.y/krb5-x.y.z and /mit/kerberos/krb5-x.y/krb5-x.y.z/doc
  • copy signature to /mit/kerberos/krb5-x.y/krb5-x.y.z.sig
  • copy README from release source code to /mit/kerberos/krb5-x.y/README-x.y.z.txt
  • generate branded HTML docs
    • HTML_LOGO=/mit/kerberos/mitkc-logo-sm.png make html
    • we don't ship the branded (with logo) docs because the logo is an MIT trademark
    • copy the resulting documentation tree to /mit/kerberos/krb5-x.y/krb5-x.y.z/doc/html
    • repeat for HTML_LOGO=... make pdf and .../doc/pdf
  • update RT configuration
  • edit web pages
    • create /mit/kerberos/krb5-x.y/krb5-x.y.z.html and check it into RCS, using similar files as an example (for the first x.y release, update krb5-x.y.html using the previous release's krb5-x.y.html as an example)
    • update /mit/kerberos/index.html with the new release numbers (possibly removing out-of-service releases) and add entries to the "Recent news" section; add old release entries to historical.html and old news items to oldnews.html
    • update /mit/kerberos/dist/index.html with new release references (possibly removing out-of-service releases); add old entries to historic.html
    • review edited web pages in a web browser and double check that release numbers and release dates have been updated
    • update /mit/kerberos/krb5-x.y/doc and /mit/kerberos/krb5-x.y/index.html symlinks
    • update /mit/kerberos/krb5-latest symlink if this is a major or minor release
    • for the first final krb5-x.y release, remove the entry from /mit/kerberos/dist/testing.html
  • send announcement to kerberos-announce
  • make followup versioning commit to release branch
    • edit src/patchlevel.h, setting KRB5_RELTAIL to "postrelease" and KRB5_RELTAG to "krb5-x.y"
    • use the commit message "Update for krb5-x.y.z-postrelease"
    • push this commit to the authoritative repository